Los Alamitos Unified School District Bond K Project

  • $126,000,000
  • Lease/Leaseback Contract with Design Assist
  • Renovations and Upgrades at 10 Sites
  • Construction scheduled in five separate phases

Phase two 6/2011 to 9/2012 Rossmoor Elementary School Modernization

  • $9,500,000 GMP
  • Project completed $1,070,000 under budget with $770,000 in contractor savings back to the owner.
  • 15 month construction schedule, phased for occupancy during construction
  • 45,000 Square feet of renovations and upgrades.
  • Construction completed on time, 9-1-12