Los Alamitos Unified School District Bond K Project

  • $126,000,000
  • Lease/Leaseback Contract with Design Assist
  • Renovations and Upgrades at 10 Sites
  • Construction scheduled in five separate phases

Phase three 6/2012 to 9/2013
Los Alamitos High School Gym & Athletics Modernization

  • $8,200,000 GMP
  • Project completed $232,793 under budget with $69,773 in contractor savings back to the owner.
  • 15 month construction schedule, phased for occupancy during construction
  • 30,000 Square feet of renovations including Gymnasium, Locker rooms, Tennis Courts, and softball Fields.
  • Construction completed on time, 1-31-13