Kyocera Cogeneration Plant Upgrade

  • $4,000,000 (Owner Provided Equipment)
  • General Construction Contract
  • New 3690 KWE of CAT gas fired generation @ 12KV and 1500 KWE of CAT diesel fired generation @ 12KV for black start and island mode.
  • A total of 1620 tons of Chilled Water production with 970 tons coming from waste heat recovery.
  • Accelerated construction schedule, 4 months start to finish.
  • While construction was performed, their was zero downtime in the manufacturing facility.