Los Alamitos Unified School District Bond K Project
$126,000,000
Lease/Leaseback Contract with Design Assist
Renovations and Upgrades at 10 Sites
Construction scheduled in five separate phases
Phase One 6/2010 to 9/2011 Los Alamitos Elementary School Modernization
$9,300,000 GMP
Project Completed $1,150,000 under budget with $1,020,000 in contractor savings back to the owner.
15 month construction schedule, phased for occupancy during construction
43,000 square feet of renovations and upgrades.
Construction completed on time, 9-1-11.